# Is Bitcoin Mining Still Profitable? What Miners' Filings Show

Published 2026-10-21 · Crypto.world Team · Crypto.world

> What bitcoin miners' own filings show since the last halving: Riot's cost per coin against what each coin earned, and why Riot, TeraWulf, Cipher, IREN and Core Scientific now rent power and buildings to AI tenants, with the risks they name.

## Block 840,000 and Riot's Cost per Coin

At 00:09 UTC on 20 April 2024, the evening of 19 April in the United States, block 840,000 became the first to pay its miner 3.125 new bitcoin instead of 6.25, plus fees. Several of the largest US-listed miners have answered the fourth halving less by mining harder than by renting out what mining gave them: power contracts, grid connections and land. In their own filings, what these companies now sell is energised megawatts, either as leased buildings or as GPU time.

The contracts are long and large: Riot Platforms, TeraWulf and Cipher have signed 15- and 20-year leases with AI tenants, and IREN a five-year GPU cloud contract with Microsoft. The two newest, Riot's and TeraWulf's 20-year leases, start paying rent from late 2027 and reach full size in 2028. The risk the companies' own disclosures name is execution: finishing buildings on the dates the contracts fix.

**In one minute**

- Riot's average hashprice: $51 per petahash per second per day in the second quarter of 2025, $34 a year later.
- Its cost to mine a bitcoin in the second quarter of 2026 was $49,912 excluding miner depreciation and $90,631 with it, against a production value of $71,667.
- Riot (191 MW, 20 years, about $9.1 billion), TeraWulf (about 401 MW, 20 years, about $19 billion) and Cipher (300 MW, 15 years, about $5.5 billion) lease buildings to AI tenants.
- IREN buys the GPUs itself for a five-year, $9.7 billion Microsoft contract.
- IREN, Cipher and Keel (formerly Bitfarms) are switching off miners to make room for tenants.

Hashprice is what a unit of hash rate earns in a day; Riot reports it in dollars per petahash per second (PH/s) per day. Its average was $51 in the second quarter of 2025 and $34 a year later. It falls when the bitcoin price drops or when more machines compete for the same blocks and fees.

Riot also reports a cost to mine, which it defines as the cost to mine one bitcoin excluding miner depreciation: power and other direct costs, net of the credits it earns by pausing operations for ERCOT's demand-response programmes, divided by the coins mined. In the quarter to 30 June 2026 the figure was $49,912, against $48,992 a year earlier. Riot attributes the rise mainly to "higher power costs and the expansion at Riot’s Kentucky facilities".

Revenue moved the other way. Riot produced 1,587 bitcoin, up from 1,426, as its deployed hash rate rose from 35.4 to 44.4 exahashes per second (EH/s), yet bitcoin mining revenue fell to $113.7 million from $140.9 million. The company cites "lower average bitcoin prices and an increase in global network hash rate". Revenue per coin mined, which Riot calls production value, dropped from $98,800 to $71,667, so cost to mine rose from 49.6% of that value to 69.6%.

Riot writes its miners off over three years and leaves that charge out of cost to mine because depreciation "is not a variable operating cost that can be avoided even if we curtail operations temporarily". Put back in, one bitcoin cost $90,631 to mine in the quarter, 126.5% of its production value; a year earlier the figures were $91,244 and 92.4%. Whether mining still pays depends on the line a reader takes: the running cost of machines already bought, or the full cost of the fleet.

## What a Miner Owns: Megawatts, Interconnects and Land

Apart from its machines, what a mining company owns is power capacity, grid connections and land. Riot's second-quarter presentation lists about 2.0 GW of available power: 1,700 MW in Texas and 300 MW in Kentucky. IREN's November 2025 announcement described its "750MW Childress, Texas campus", and its co-chief executive, Daniel Roberts, spoke of "our 3GW secured power portfolio in North America". Riot's chief executive made the same case in August 2026.

> Our platform stands apart through three elements working together: multi-gigawatt-scale power capacity that is already fully approved and energized, in-house data center development expertise, and the ability to engineer custom infrastructure for computing's most demanding workloads. — Jason Les, CEO, Riot Platforms

Leases are priced in a narrower unit. Critical IT load is the power available to the tenant's computing equipment, while a site's gross capacity also covers cooling and the rest of the plant. Cipher's Fluidstack lease at Barber Lake was signed for 244 MW gross and 168 MW of IT load, and TeraWulf's Justified campus in Kentucky has access to up to about 480 MW of gross power for about 401 MW of critical IT.

On 30 October 2025 Core Scientific's stockholders did not approve a merger with CoreWeave, and the company said it was "in the process of converting most of our existing facilities to support artificial intelligence-related workloads", while mining still earned most of its revenue. In the second quarter of 2026, colocation brought in $136.7 million of $164.2 million revenue and self-mining $21.5 million, against $62.4 million a year earlier. In August its chief executive, Adam Sullivan, said site purchases that year had added "more than 600 MW of leasable power to our portfolio".

## Four Contracts, as Filed

Under a contract dated 2 November 2025, an IREN subsidiary will give Microsoft access to NVIDIA GB300 GPUs in four liquid-cooled buildings at Childress, Horizon 1 to 4, with about 200 MW of IT load, over a five-year average term. The total contract value is about $9.7 billion through 2031, with 20% of each tranche paid before delivery; Dell is supplying the GPUs and related equipment for about $5.8 billion. Microsoft accepted Horizon 1 in August 2026, and IREN targets Horizons 3 and 4 for the fourth quarter.

Cipher Mining, renamed Cipher Digital in February 2026, announced its lease with Amazon Web Services on 3 November 2025: about $5.5 billion over 15 years for 300 MW of turnkey space and power at its Black Pearl site near Wink, Texas. Its chief executive, Tyler Page, called it "our first direct lease with a Tier 1 hyperscaler". Rent was first due from August 2026, then targeted for the fourth quarter in the annual report; after an amendment the tenant requested, Cipher said in August that rent had commenced.

On 6 July 2026 TeraWulf announced a lease with Anthropic for about 401 MW of critical IT load at its Justified Data campus in Hawesville, Kentucky. Rent starts as phases are delivered from the second half of 2027 and runs 20 years, with two five-year renewal options. TeraWulf expects about $19 billion of contracted revenue over the initial term, and up to about $33 billion with both options. It also agreed to sell its 50.1% stake in the 168 MW Abernathy joint venture to a Fluidstack-led group for about $530 million.

Riot announced its lease on 10 August 2026. A tenant it describes only as "a leading frontier AI lab" will take 191 MW of critical IT at the Rockdale campus in Texas: 96 MW in December 2027 and the rest by June 2028, for an initial term to June 2048. Riot expects about $9.1 billion of contract revenue over that term, or about $16.1 billion if two five-year extensions are exercised. Les said its announcement "marks a defining moment in our evolution into a leading developer of large-scale data centers".

With the AMD lease announced in January, Riot counts 241 MW and about $9.8 billion contracted. None of these values is revenue earned. In the second quarter of 2026 Riot booked $23.2 million of data-centre revenue, of which $4.9 million was lease income and $18.3 million fit-out work reimbursed by the tenant, and TeraWulf $31.9 million of HPC lease revenue at its Lake Mariner campus in New York. IREN's AI cloud revenue for the year to 30 June 2026 was $128.8 million.

## GPU Cloud or Powered Shell: Who Carries Which Risk

The contracts follow two models. IREN sells computing as a service: it buys the GPUs, so the capital cost, the depreciation and the risk that the chips age out sit with IREN. Its annual report warns that "the equipment we deploy is subject to rapid technological change and obsolescence". Its terms are short: the Microsoft contract has a five-year average term, and in July 2026 IREN put the weighted average across its customer contracts at about four years.

IREN pays for the hardware with borrowing and customer money. At its August 2026 results, $3.6 billion of investment-grade GPU financing for the Microsoft contract carried an average 6.0% and, with Microsoft's prepayments, funded 96% of the related GPU spending. Customers without an investment-grade rating cost more to finance: a $2.4 billion facility led by Blue Owl and PIMCO for those deployments carried a fixed 9.0%.

Riot, TeraWulf, Cipher and Core Scientific lease buildings instead. The tenant brings its own computers; the developer delivers shell, power and cooling, pays for construction and signs for 10 to 20 years. Riot's August presentation puts the 191 MW project at $2.1 billion to $2.3 billion, an illustrative $11 million to $12 million per IT megawatt of new construction, and anticipates net operating income margins of 80% to 90%.

A lease depends on the tenant's ability to pay, so several developers lean on third parties' credit. Cipher said in November 2025 that Google backstops $1.4 billion of Fluidstack's lease obligations at Barber Lake, and in July 2026 a delivered building at TeraWulf's Lake Mariner made $600 million of Google's credit support for Fluidstack effective. TeraWulf expects Anthropic's payments to be "supported by an investment-grade credit". In August Riot took an interim facility of up to $573 million from lenders with Morgan Stanley as agent "while the investment-grade credit backstop is finalized".

## Where the Hashrate Goes

Riot still mines at scale: its 44.4 EH/s at the end of June was about 4.6% of the network's quarterly average, by its count. But it sells coins to build. In the first half of 2026 it mined 3,060 bitcoin and sold 9,665 for $732.5 million, calling bitcoin sales the "primary funding source" for the equity share of data-centre spending. On 21 September it repaid a Coinbase Credit loan of up to $200 million, releasing the bitcoin pledged against it (5,821 coins at 30 June).

IREN is leaving mining. It began decommissioning mining hardware in the year to June 2026 and aims to substantially complete the transition by 31 December 2026; installed capacity was about 23.2 EH/s at 30 June, on roughly 380 MW. Non-cash impairments of $638.8 million in the year related "primarily" to that decommissioning, and quarterly mining revenue fell from $111.2 million in January to March 2026 to $66.7 million in April to June.

Cipher stopped mining at Black Pearl in February 2026 because of the AWS lease; it still mines at Odessa, about 11.6 EH/s and 346 bitcoin in the second quarter, while negotiating an HPC lease there. TeraWulf's digital asset revenue fell to $12.8 million in the second quarter of 2026 from $47.6 million a year earlier, with parts of its Lake Mariner mining infrastructure being repurposed. Core Scientific is converting its remaining mining facilities "as circumstances allow".

Bitfarms went furthest: in November 2025 its chief executive, Ben Gagnon, said it would "wind down our Bitcoin mining business in 2026 and 2027", and on 1 April 2026 it moved its domicile to the United States as Keel Infrastructure. By August Keel reported that it had decommissioned all its US bitcoin mining operations, and it was still negotiating with prospective tenants at its three priority sites. Gagnon's summary in August: "Power is the constraint. Everything else is downstream of it."

Network hash rate has moved both ways. In the quarterly averages Riot takes from Blockchain.com, it rose from 876 EH/s in the second quarter of 2025 to 1,071 EH/s in the fourth, then fell to 957 EH/s in the second quarter of 2026. Blockchain.com's daily estimates averaged about 920 EH/s from July to September 2026 and about 1,000 EH/s over 1 to 18 October.

## The Risks the Filings Name

The first risk is the calendar. IREN's agreement gives Microsoft, subject to a cure period, a right to terminate if IREN's subsidiary "fails to meet agreed delivery dates". Cipher's annual report says its tenants' guarantees take effect only after rent commencement and are subject to "event of default triggers or caps on liability". If completion is delayed, tenants may be able to end the lease, and "Such termination events would not trigger the tenants’ guarantee either."

Schedules have already moved. Cipher's annual report targeted the first phase of Barber Lake by 30 September 2026; in September, citing change orders and evolving tenant requirements, it agreed deliveries from the fourth quarter of 2026 into early 2027. It will bear the first $359.3 million of costs above the initial budget, with the tenant reimbursing half of any excess beyond that over 20 years. The amendment also added a 10-year commitment from an unnamed AI lab, lifting contracted revenue there from $3.8 billion to over $9 billion.

Concentration is the second risk. IREN's annual report says the Microsoft contract and a five-year, $3.4 billion contract with NVIDIA signed in May 2026 "represent a substantial majority of our contracted revenue". Riot's two leases at Rockdale are with AMD and one unnamed lab.

Financing and the grid come third. The buildings are paid for with money raised before rent arrives, from Riot's interim facility to the $850 million of convertible notes Cipher priced in October 2026. Core Scientific reported in September that capacity at its Pecos and Hunt sites in Texas had only conditional approval in ERCOT's "Batch Zero" process, and Kentucky's Public Service Commission approved TeraWulf's power agreement for Hawesville in August.

The releases' cautionary language names the same risks. Riot lists "construction plans, delays, supply chain issues, permitting or regulatory hurdles, and unforeseen technical challenges". TeraWulf cites its ability to finish campuses "in a timely manner or within anticipated cost estimates", and its chief executive, Paul Prager, set the goal in August: "Our objective is not simply to accumulate megawatts—it is to build a durable, capital-efficient platform that compounds value for shareholders."

## Dates Ahead

- November 2026: Riot's next 10 MW for AMD at Rockdale.
- Fourth quarter of 2026: IREN's Horizons 3 and 4 for Microsoft, and the first rent at Cipher's Barber Lake.
- 31 December 2026: IREN's target for substantially leaving mining, and the deadline for $150 million of TeraWulf's Abernathy proceeds; about $130 million more is due by 30 April 2027.
- 2027: Riot's last 15 MW for AMD in May, TeraWulf's first Anthropic capacity in the second half, and Riot's first 96 MW for its unnamed tenant in December.
- 2028: TeraWulf's 401 MW in full by early 2028 and Riot's 191 MW by June, the same year block 1,050,000 halves the subsidy again, to 1.5625 BTC.

## Sources

1. [Riot Platforms, Q2 2026 results and 191 MW lease, Form 8-K Exhibit 99.1 (10 August 2026)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926093406/riot-20260810xex99d1.htm) sec.gov
2. [Riot Platforms, Q2 2026 earnings presentation, Form 8-K Exhibit 99.2 (10 August 2026)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926093406/riot-20260810xex99d2.htm) sec.gov
3. [Riot Platforms, Form 10-Q for the quarter ended 30 June 2026](https://www.sec.gov/Archives/edgar/data/1167419/000110465926093448/riot-20260630x10q.htm) sec.gov
4. [Riot Platforms, Form 8-K: $573 million credit agreement with Morgan Stanley Senior Funding as agent (14 August 2026)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926097330/riot-20260810x8k.htm) sec.gov
5. [Riot Platforms, Form 8-K: prepayment and termination of the Coinbase Credit facility (25 September 2026)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926111003/riot-20260921x8k.htm) sec.gov
6. [Riot Platforms, Form 10-K for 2025 (halving history)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926022322/riot-20251231x10k.htm) sec.gov
7. [TeraWulf, Anthropic lease at Justified Data campus and sale of Abernathy JV interest (6 July 2026)](https://investors.terawulf.com/news-events/press-releases/detail/142/) investors.terawulf.com
8. [TeraWulf, Form 8-K Item 8.01: Justified Data Campus Lease and Abernathy Transaction (6 July 2026)](https://www.sec.gov/Archives/edgar/data/1083301/000110465926080583/tm2619468d1_8k.htm) sec.gov
9. [TeraWulf, Q2 2026 results, Form 8-K Exhibit 99.1 (5 August 2026)](https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm) sec.gov
10. [TeraWulf, Muskie Data Campus power expansion release, Form 8-K Exhibit 99.1 (5 October 2026)](https://www.sec.gov/Archives/edgar/data/1083301/000162828026064757/muskieexpansionpr.htm) sec.gov
11. [IREN, $9.7bn AI cloud contract with Microsoft, Form 8-K Exhibit 99.1 (3 November 2025)](https://www.sec.gov/Archives/edgar/data/1878848/000114036125040072/ef20058139_ex99-1.htm) sec.gov
12. [IREN, Form 8-K Item 1.01: Microsoft Agreement and Dell Purchase Agreement (3 November 2025)](https://www.sec.gov/Archives/edgar/data/1878848/000114036125040072/ef20058139_8k.htm) sec.gov
13. [IREN, Horizon 1 delivered to Microsoft, Form 8-K Exhibit 99.1 (13 August 2026)](https://www.sec.gov/Archives/edgar/data/1878848/000114036126032638/ef20080141_ex99-1.htm) sec.gov
14. [IREN, FY26 results, Form 8-K Exhibit 99.1 (27 August 2026)](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000051/irenreportsfy26results.htm) sec.gov
15. [IREN, Form 10-K for the year ended 30 June 2026](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000052/iren-20260630.htm) sec.gov
16. [IREN, new customer contracts and weighted average contract term, Form 8-K Exhibit 99.1 (20 July 2026)](https://www.sec.gov/Archives/edgar/data/1878848/000114036126028871/ef20078253_ex99-1.htm) sec.gov
17. [Cipher Mining, Q3 2025 business update and AWS lease, Form 8-K Exhibit 99.1 (3 November 2025)](https://www.sec.gov/Archives/edgar/data/1819989/000181998925000110/nov3_earningspressreleasex.htm) sec.gov
18. [Cipher Mining, business update presentation, Form 8-K Exhibit 99.2 (3 November 2025)](https://www.sec.gov/Archives/edgar/data/1819989/000181998925000110/ciphermining_businessupd.htm) sec.gov
19. [Cipher Digital, Form 10-K for 2025](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) sec.gov
20. [Cipher Digital, Form 8-K Item 5.03: name change from Cipher Mining (20 February 2026)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000007/cifr-20260220.htm) sec.gov
21. [Cipher Digital, Q2 2026 business update, Form 8-K Exhibit 99.1 (4 August 2026)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/q226_earningsxprxdraftxvf.htm) sec.gov
22. [Cipher Digital, Q2 2026 presentation, Form 8-K Exhibit 99.2 (4 August 2026)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm) sec.gov
23. [Cipher Digital, Barber Lake lease amendment, Form 8-K Exhibit 99.1 (25 September 2026)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000043/barberlakeleaseamendmentpr.htm) sec.gov
24. [Cipher Digital, pricing of $850 million convertible notes, Form 8-K Exhibit 99.1 (14 October 2026)](https://www.sec.gov/Archives/edgar/data/1819989/000119312526421035/d77312dex991.htm) sec.gov
25. [Core Scientific, termination of merger agreement with CoreWeave, Form 8-K Exhibit 99.1 (30 October 2025)](https://www.sec.gov/Archives/edgar/data/1839341/000114036125039808/ef20057995_ex99-1.htm) sec.gov
26. [Core Scientific, Form 8-K Item 1.02 (30 October 2025)](https://www.sec.gov/Archives/edgar/data/1839341/000114036125039808/ef20057995_8k.htm) sec.gov
27. [Core Scientific, Q2 2026 results, Form 8-K Exhibit 99.1 (28 July 2026)](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000013/q22026corescientificinc-ea.htm) sec.gov
28. [Core Scientific, completion of Polaris DS acquisition, Form 8-K Exhibit 99.1 (14 August 2026)](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000018/polarisclosingvf20260814.htm) sec.gov
29. [Core Scientific, Form 8-K Item 7.01: ERCOT power status of Texas sites (10 September 2026)](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000023/core-20260910.htm) sec.gov
30. [Bitfarms, material change report: Washington site conversion and mining wind-down, Form 6-K Exhibit 99.2 (13 November 2025)](https://www.sec.gov/Archives/edgar/data/1812477/000121390025109575/ea026548201ex99-2_bitfarms.htm) sec.gov
31. [Bitfarms rebrands as Keel Infrastructure and completes US redomiciliation, Form 8-K Exhibit 99.1 (1 April 2026)](https://www.sec.gov/Archives/edgar/data/1812477/000121390026038080/ea028450001ex99-1.htm) sec.gov
32. [Keel Infrastructure, Q2 2026 results, Form 8-K Exhibit 99.1 (10 August 2026)](https://www.sec.gov/Archives/edgar/data/1812477/000181247726000021/a202689finalprkeelq22026ea.htm) sec.gov
33. [mempool.space, block 840,000 (timestamp 2024-04-20 00:09:27 UTC; 3.125 BTC subsidy)](https://mempool.space/block/0000000000000000000320283a032748cef8227873ff4872689bf23f1cda83a5) mempool.space
34. [Blockchain.com, total hash rate chart (daily estimates, read 21 October 2026)](https://www.blockchain.com/explorer/charts/hash-rate) blockchain.com

## Related stories

- [Is Base Decentralized? Ethereum's Blobs, Rollup Stages, Sequencers](https://crypto.world/industries/ethereum-blobs-rollup-stages-sequencer-outages)
- [Aave Liquidations Under Stress: Where DeFi Lending Actually Broke](https://crypto.world/industries/defi-lending-liquidations-oracles-curators)
- [How Crypto ETFs Work: In-Kind Baskets, Custody and Staking](https://crypto.world/industries/crypto-etf-structure-in-kind-custody-staking)

## Explore

[More articles](https://crypto.world/industries)

---

Canonical: https://crypto.world/industries/bitcoin-miners-halving-ai-data-center-leases