# MARA sells bitcoin to repay debt as it targets AI infrastructure

Published 2026-11-10 · Crypto.world Team · Crypto.world

> MARA sold 3,891 BTC in the third quarter and later used bitcoin-sale proceeds to repay $750 million of BTC-backed debt. The company is using its power and compute assets to pursue AI infrastructure while keeping bitcoin mining as a core business.

## Bitcoin sales and debt reduction

MARA sold 3,891 BTC in the third quarter at an average price of $75,300, while mining 2,247 BTC. It held 34,012 BTC at quarter-end, including net digital assets receivable.

Source [sec.gov](https://www.sec.gov/Archives/edgar/data/1507605/000150760526000026/q326shareholderletter.htm)

After the quarter ended, MARA repaid $750 million of BTC-backed debt using proceeds from bitcoin sales. The repayment released all bitcoin pledged as collateral, leaving less than 5% of its holdings loaned or pledged, the company said. The company said it had reduced total debt by $1.4 billion, or 37%, since the beginning of the year.

The company plans to keep using bitcoin to build cash for AI infrastructure opportunities, convertible-note puts and potential share repurchases. It also said the debt repayment reduced its exposure to bitcoin price volatility.

## Mining remains part of the plan

Bitcoin mining remains a core business and a way to monetize power while the company develops other infrastructure opportunities, the company said. The company described its wider strategy as an effort to increase the value it captures from power, land and compute, rather than a move away from bitcoin.

Third-quarter revenue was $164.2 million, down 35% from $252.4 million in the same quarter of 2025. Net income was $632.1 million, compared with $123.1 million a year earlier, while adjusted EBITDA was $857.7 million, up from $395.6 million in Q3 2025.

Its energized hashrate rose 18% to 71.2 EH/s from 60.4 EH/s in Q3 2025. The company said it mined the quarter’s bitcoin at an average price of $71,688 and made no bitcoin purchases in Q3 2026.

## Power and data-center development

The company said it is evolving into an energy-backed digital infrastructure company spanning power, land and compute. Its AI and high-performance computing strategy is to turn powered land into contracted infrastructure for large compute customers, while Exaion provides private cloud infrastructure and AI services.

The company owns and operates approximately 1 GW across sites in the United States and international markets. Subject to the Long Ridge closing and Matagorda energization, the company said it expects the portfolio to reach over 4 GW.

The company is targeting two lease signings before year-end, though it warned the timing could slip into next year. It said discussions with prospective tenants were in advanced stages and that its teams had hosted potential tenants across nearly all of its sites.

At Long Ridge, the company had received FERC approval and expected to close the transaction in the coming weeks, subject to customary conditions, it said. The plant is currently authorized to sell 485 MW and is expected to reach its 505 MW nameplate capacity in the first half of 2027, the company said.

The company also secured rights to develop a Matagorda County, Texas, site with up to 2 GW of power capacity. The site was classified as a studied load in ERCOT’s Batch Zero process, the company said, and it is working with the utility to bring power online; payments to the sellers are contingent on power approval, and the company said it had made none to date.

## Exaion contract

Exaion signed a four-year, $79 million GPU-as-a-service contract with its first U.S. customer on 100% take-or-pay terms. The company reported a pipeline of over $3 billion in total contract value, with approximately $1 billion targeted for delivery by the end of 2027, but said those prospects are not contracted or committed.

The shareholder letter said the company will continue to assess bitcoin sales, debt, cash and access to capital together as it allocates resources among operations, debt reduction and infrastructure projects.

## Sources

1. Original source · Company filing [U.S. Securities and Exchange Commission](https://www.sec.gov/Archives/edgar/data/1507605/000150760526000026/q326shareholderletter.htm) sec.gov

Other pages read

2. [MARA](https://ir.mara.com/sec-filings/all-sec-filings/content/0001507605-26-000026/q326shareholderletter.htm) ir.mara.com

## Related stories

- [Core Scientific’s $3.3B AI Debt Carries a $256M Annual Coupon](https://crypto.world/news/core-scientific-3-3b-ai-debt-annual-coupon)
- [Bitdeer reports $2.9B AI cloud backlog as quarterly loss widens](https://crypto.world/news/bitdeer-ai-cloud-backlog-quarterly-loss)
- [Cipher Digital Posts First HPC Rent as Mining Revenue Falls 71%](https://crypto.world/news/cipher-digital-hpc-revenue-mining-falls-q3-2026)
- [BitFuFu third-quarter revenue falls 79.1% as self-mining share rises to 48.8%](https://crypto.world/news/bitfufu-q3-2026-revenue-falls-self-mining-share-rises)
- [BitGo reports 50.9% revenue drop as normalized assets grow](https://crypto.world/news/bitgo-revenue-down-normalized-assets-grow-q3-2026)

## Explore

[More articles](https://crypto.world/news)

---

Canonical: https://crypto.world/news/mara-bitcoin-sales-debt-ai-infrastructure